On the 8th of Feb 2010, Al Habib Contracting, the main contractor for the RO 0.92 Mil Water Supply project in Salalah was invited for the formal opening Ceremony of the project.
The project consists of 11 pumping systems with bore hole pumps and 24 kms of pressure cross country piping. Eight water storage tanks were constructed, with acapacity of 55,000 gallon, and over head line works of 5 KMS.
The project was completed in 14 months, with peak time manpower of 40.